NOGRR #232 · Revision Request
NOGRR232 Related to NPRR1093, Load Resource Participation in Non-Spinning Reserve
ReasonAddresses current operational issues / Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board) / Market efficiencies or enhancements
Created2021-09-21
Approved2021-10-28
Sections Affected
2.3 and 2.3.2.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guide with revisions from NPRR1093 to allow Load Resources that are not Controllable Load Resources to provide Non-Spinning Reserve (Non-Spin) Ancillary Service.
Timeline
- Sep 1 '21
-
Sep 21 '21
ROS ROS Email Vote re NOGRR232ROSRecommended for Approval Urgent status Recommended for approval Forwarded → TAC“To grant NOGRR232 Urgent status; to recommend approval of NOGRR232 as submitted; and to forward to TAC NOGRR232 and the Impact Analysis” — Passed→ TAC for consideration
-
Sep 29 '21
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Recommended for approval“To recommend approval of NOGRR232 as recommended by ROS in the 9/21/21 ROS Report” — Passed→ Board for consideration
-
Oct 22 '21
BOARD Board of Directors Special MeetingBOARDRecommended for Approval Recommended for approval“To recommend approval of NOGRR232 as recommended by TAC in the 9/29/21 TAC Report” — Passed→ PUCT for consideration
-
Oct 28 '21
PUCTPUCTApproved Approved“To approve NOGRR232 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021” — Passed
-
—
Posted since the last meeting