NOGRR #226 · Revision Request

NOGRR226  Addition of Supplemental UFLS Stages

Approved sponsor LCRA posted 2021-05-14 ercot.com
ReasonAddresses current operational issues
Created2021-06-03
Approved2023-01-26
Sections Affected
2.6.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds provisions for Transmission Operator (TO) “anti-stall” automatic firm Load shedding at 59.5 Hz in order to improve reliability by mitigating the risk of a total system-wide Blackout.
Timeline