NOGRR223  Add Phasor Measurement Recording Equipment Requirement to Modified Generating Facilities in Interconnection Process

Approved sponsor ERCOT posted 2021-02-09 ercot.com
ReasonAddresses current operational issues
Created2021-03-04
Approved2021-10-07
Sections Affected
6.1.3.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds the requirement to have phasor measurement recording equipment at existing facilities that have an aggregated generating capacity above 20 MVA at a single site following any modification that is described in paragraph (1)(b) of Planning Guide Section 5.1.1, Applicability, in order to enter the Generation Resource Interconnection or Change Request process.