ERCOT·WATCH Search ercot.com  ⌕
NOGRR #174 · Revision Request

NOGRR174  AVR and PSS Testing Requirements

Approved sponsor Luminant Generation posted 2017-12-27 ercot.com
ReasonRegulatory requirements
Created2018-01-11
Approved2018-08-07
Sections Affected
2.2.52.2.6
Summary
This Nodal Operating Guide Revision Request (NOGRR) harmonizes the ERCOT Automatic Voltage Regulator (AVR) and Power System Stabilizer (PSS) testing requirements with the recently approved North American Electric Reliability Corporation (NERC) Standard MOD-026-1, Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions.
Timeline