NOGRR #131 · Revision Request
NOGRR131 Clarification for Generation Resources During an EEA
ReasonTo address current operational issues.
Created2014-05-19
Sections Affected
4.5.3.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies language that when ERCOT is in an Energy Emergency Alert (EEA), Qualified Scheduling Entities (QSEs) must receive authorization from ERCOT prior to manually removing an On-Line Resource.
Timeline
- Apr 30 '14
-
May 19 '14
OWG OWG MeetingOWGRecommended for Approval Recommended for approval Amended by the May 19 '14 Luminant comments“To recommend approval of NOGRR131 as amended by the 5/19/14 Luminant comments.” — Passed→ OWG for IA review
-
Jun 25 '14
OWG OWG MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“To endorse and forward the 5/19/14 OWG Report and Impact Analsyis for NOGRR131 to ROS.” — Passed→ ROS for consideration
-
Jul 10 '14
ROS ROS MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR131 as recommended by OWG in the 6/25/14 OWG Report.” — Passed→ TAC for consideration
- Jul 22 '14
-
Jul 31 '14
TAC TAC MeetingTACApproved Recommended for approval“To approve as recommended by ROS in the 7/10/14 ROS Report.” — Passed
-
—
Posted since the last meeting