ERCOT·WATCH Search ercot.com  ⌕
NOGRR #124 · Revision Request

NOGRR124  Additional VRT Requirement for IRRs

Approved sponsor ERCOT posted 2013-08-30 ercot.com
ReasonTo maintain system reliability by establishing additional VRT requirements for IRRs.
Created2013-09-18
Sections Affected
2.9.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) specifies new high Voltage Ride-Through (VRT) requirements for Intermittent Renewable Resources (IRRs) and prohibits IRRs from tripping for events that are less severe than the defined thresholds and occur for shorter time durations.
Timeline