NOGRR #115 · Revision Request
NOGRR115 Update to List of CREZ Circuits and Stations
ReasonAt the CREZ Coordination meeting held on March 20, 2013, it was requested that the Operations Working Group (OWG) review Section 7.1.2 and revise the list of CREZ circuits and stations to align with 345 kV circuits and stations.
Created2013-05-15
Sections Affected
7.17.1.27.5 (new)
Summary
This NOGRR updates the list of CREZ circuits and stations to align with installed 345kV circuits and stations. Non-substantive revisions are also proposed to Section 7.1.
Timeline
- Apr 26 '13
-
May 15 '13
OWG Operations Working Group (OWG) MeetingsOWGRecommended for Approval Recommended for approval Amended by the OWG comments“Consensus to recommend approval of NOGRR115 as revised by OWG”→ OWG IA Review
-
Jun 19 '13
OWG Operations Working Group (OWG) MeetingsOWGRecommended for Approval Recommended for approval Forwarded → ROS“To endorse and forward the 5/15/13 OWG Report and Impact Analysis for NOGRR115 to ROS”→ ROS Consideration
-
Jul 11 '13
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR115 as recommended by OWG in the 6/19/13 OWG Report” — Passed→ TAC Consideration
-
Sep 5 '13
TAC Technical Advisory Committee (TAC) MeetingTACApproved Recommended for approval“To approve NOGRR115 as recommended by ROS in the 7/11/13 ROS Report” — Passed
-
—
Posted since the last meeting