NOGRR #98 · Revision Request
NOGRR098 Change of Facility Submission Time Lines to Align with Protocols
ReasonTo align and clarify the Nodal Operating Guides with paragraph (10) of Protocol Section 3.10, Network Operations Modeling and Telemetry, and paragraph (3) of Protocol Section 3.10.1, Time Line for Network Operations Model Changes, which outlines the time line for Transmission Service Provider (TSP) and Resource Entity submissions of Network Operations Model updates.
Created2012-06-13
Sections Affected
5.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies the submission time line for facility reactive capability and other modeling information.
Timeline
- May 25 '12
-
Jun 13 '12
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval“Consensus to recommend approval of NOGRR098 as submitted”→ OWG IA Review
-
Jul 18 '12
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“Consensus to endorse and forward the 6/13/12 OWG Report and Impact Analysis for NOGRR098 to ROS”→ ROS Consideration
-
Aug 16 '12
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR098 as recommended by OWG in the 7/18/12 OWG Report” — Passed→ TAC Consideration
-
Sep 7 '12
TAC Technical Advisory Committee (TAC) MeetingTACApproved Recommended for approval“To approve NOGRR098 as recommended by ROS in the 8/16/12 ROS Report” — Passed
-
—
Posted since the last meeting