ERCOT·WATCH Search ercot.com  ⌕
NOGRR #87 · Revision Request

NOGRR087  Reinsertion of Network Operations Modeling Requirements

Approved Urgent sponsor Planning Working Group (PLWG) posted 2011-11-30 ercot.com
ReasonThe intent of the Planning Working Group (PLWG) was to retain Section 5.5, System Modeling Information, when deleting Section 5, Planning, of the Nodal Operating Guides via NOGRR058, Deletion of Section 5, Planning.
Created2012-01-05
Sections Affected
55.1
Summary
This NOGRR reinserts a portion of the Nodal Operating Guide that was inadvertently deleted.
Timeline