NOGRR #86 · Revision Request
NOGRR086 Clarification of Seasonal Unit Capability Testing Requirements
ReasonThe existing language conflicts with the testing requirement in Protocol Section 8.1.1.2, General Capacity Testing Requirements. Seasonal unit capability testing occurs each Season, as defined in the Protocols.
Created2011-12-14
Sections Affected
3.3.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies the seasonal unit capability testing requirement.
Timeline
- Nov 1 '11
-
Dec 14 '11
OWG Operations Working Group (OWG) MeetingOWGDeferred/Tabled Tabled“Consensus to table NOGRR086”→ OWG Language Consideration
-
Jan 6 '12
Listed without action at 2 meetings (Jan 6 '12 – Jan 11 '12)
-
Jan 30 '12
OWG Operations Working Group (OWG) MeetingOWGDeferred/Tabled Tabled“To table NOGRR086for one month.”→ OWG for consideration.
-
Feb 15 '12
OWG Operations Working Group (OWG) MeetingOWGDeferred/Tabled Tabled“Consensus to table NOGRR086.”→ OWG for consideration.
-
Apr 18 '12
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval Amended by the OWG comments“Consensus to recommend approval of NOGRR086 as revised by OWG.”→ OWG for Impact Analysis review.
-
May 16 '12
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“Consensus to endorse and forward the 4/18/12 OWG Report and the Impact Analysis for NOGRR086 to ROS.”→ ROS for consideration.
-
Jun 14 '12
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR086 as recommended by OWG in the 5/16/12 OWG Report.” — Passed→ TAC for consideration.
-
Jun 28 '12
TAC Technical Advisory Committee (TAC) MeetingTACDeferred/Tabled Tabled“To table NOGRR086.” — Passed→ TAC for consideration.
-
Sep 7 '12
TAC Technical Advisory Committee (TAC) MeetingTACApproved Recommended for approval“To approve NOGRR086 as recommended by ROS in the 6/14/12 ROS Report.”
-
—