ERCOT·WATCH Search ercot.com  ⌕
NOGRR #77 · Revision Request

NOGRR077  Synchronization with NPRR379, EILS Dispatch Sequence and Performance Criteria Upgrades

Approved sponsor ERCOT posted 2011-07-05 ercot.com
ReasonTo synchronize the Nodal Operating Guides with NPRR379.
Created2011-07-20
Sections Affected
4.5.3.3 and 9.1.4
Summary
This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 379, EILS Dispatch Sequence and Performance Criteria Upgrades, which provides ERCOT Operators with enhanced flexibility for managing grid conditions during an Energy Emergency Alert (EEA) by requiring dispatch of EILS prior to or in conjunction with dispatch of Load Resources providing Responsive Reserve (RRS) in EEA Level 2.
Timeline