NOGRR #70 · Revision Request
NOGRR070 Synchronization with NPRR356, EEA Changes Related to Dispatch Instructions and BLTs
ReasonThe changes to the EEA process will allow ERCOT to be more efficient in making Hotline calls to Qualified Scheduling Entities (QSEs).
Created2011-06-15
Sections Affected
4.5.3.14.5.3.24.5.3.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 356, EEA Changes Related to Dispatch Instructions and BLTs, which was approved by the ERCOT Board on August 16, 2011; and which changes the need to issue Dispatch Instructions to suspend any ongoing ERCOT-required generating unit or Resource performance testing and moves the requirement to inquire about the availability of Block Load Transfers (BLTs) from Energy Emergency Alert (EEA) Level 2A to EEA Level 2B.
Timeline
- May 4 '11
-
Jun 15 '11
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval Amended by the OWG comments“To recommend approval of NOGRR070 as revised by OWG.” — Passed→ Impact Analysis Consideration
-
Jul 20 '11
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“To endorse and forward the 6/15/11 OWG Report and Impact Analysis for NOGRR070 to ROS”→ ROS Consideration
-
Aug 11 '11
ROS ROS MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR070 as recommended by OWG in the 7/20/11 OWG Report” — Passed→ TAC Consideration
-
Sep 1 '11
TAC TAC MeetingTACApproved Recommended for approval“To approve NOGRR070 as recommended by ROS in the 8/11/11 ROS Report” — Passed
-
—
Posted since the last meeting