NOGRR #68 · Revision Request

NOGRR068  Hydro-Responsive Reserve

Approved Urgent sponsor ERCOT posted 2011-03-31 ercot.com
ReasonThe frequency requirement existed in zonal Operating Guide Section 2.5.2.3, Types of Responsive Reserve, but were inadvertently omitted from the Nodal Operating Guides
Created2011-04-11
Sections Affected
2.3.1.12.3.1.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds frequency requirement for the deployment of synchronous condenser fast response service to the Nodal Operating Guide.