NOGRR #68 · Revision Request
NOGRR068 Hydro-Responsive Reserve
ReasonThe frequency requirement existed in zonal Operating Guide Section 2.5.2.3, Types of Responsive Reserve, but were inadvertently omitted from the Nodal Operating Guides
Created2011-04-11
Sections Affected
2.3.1.12.3.1.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds frequency requirement for the deployment of synchronous condenser fast response service to the Nodal Operating Guide.
Timeline
- Mar 31 '11
- Apr 11 '11
- Apr 20 '11
-
May 12 '11
ROS ROS MeetingROSDeferred/Tabled Tabled“To table NOGRR068 for one month” — Passed→ ROS Consideration
-
Jun 16 '11
ROS ROS MeetingROSRecommended for Approval Recommended for approval Forwarded → TAC“To recommend approval of NOGRR068 as submitted with a proposed effective date "of upon TAC approval" and to forward NOGRR068 and the Impact Analysis to TAC.” — Passed→ TAC consideration
-
Jul 7 '11
TAC TAC MeetingTACApproved Recommended for approval Amended by the Jul 6 '11 LCRA comments“To approve NOGRR068 as recommended by ROS in the 6/16/11 ROS Report and as amended by the 7/6/11 LCRA comments” — Passed