NOGRR #56 · Revision Request
NOGRR056 Synchronization with NPRR291, Reduce the Comment Period for NPRRs and SCRs
ReasonAs a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since NOGRRs have a similar initial comment period, proposed revisions to the Nodal Operating Guide revision process are included in this NOGRR to align with the Nodal Protocol revision process.
Created2011-02-16
Sections Affected
1.3.4.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) reduces the comment period for NOGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Operations Working Group (OWG) meeting.
Timeline
- Dec 27 '10
-
Feb 16 '11
OWG OWG MeetingOWGRecommended for Approval Recommended for approval“Consensus to recommend approval of NOGRR056 as submitted”→ OWG IA Review
-
Mar 7 '11
OWG OWG MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“Consensus to endorse and forward the 2/16/11 OWG Report and Impact Analysis for NOGRR056 to ROS”→ ROS Consideration
-
Apr 11 '11
ROS ROS MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR056 as recommended by OWG in the 3/7/11 OWG Report” — Passed→ TAC Consideration
- Apr 20 '11
-
May 5 '11
TAC TAC MeetingTACApproved Recommended for approval“To approve NOGRR056 as recommended by ROS in the 4/11/11 ROS Report” — Passed
-
—