NOGRR #54 · Revision Request
NOGRR054 Change in Facilitator for the Annual Operations Training Seminar
ReasonThe operations training seminar provides a forum for Market Participants to meet and analyze topics and issues related to the operation of the ERCOT System. As the Independent System Operator (ISO) in the ERCOT Region, ERCOT is in the best position to provide the annual Operations Training Seminar.
Created2011-01-19
Approved2011-05-17
Sections Affected
1.5.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) changes the responsibility of the annual Operations Training Seminar from the Texas Reliability Entity (TRE) to ERCOT.
Timeline
- Dec 21 '10
-
Jan 19 '11
OWG OWG MeetingOWGRecommended for Approval Recommended for approval“Consensus to recommend approval of NOGRR054 as submitted”→ OWG IA Review
-
Feb 16 '11
OWG OWG MeetingOWGRecommended for Approval Recommended for approval Forwarded → ROS“Consensus to endorse and forward the 1/19/11 OWG Report and Impact Analysis for NOGRR054 to ROS”→ ROS Consideration
-
Mar 10 '11
ROS ROS MeetingROSRecommended for Approval Recommended for approval“To recommend approval of NOGRR054 as recommended by OWG in the 2/16/11 OWG Report.” — Passed→ TAC Consideration
-
Apr 7 '11
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NOGRR054 as recommended by ROS in the 3/10/11 ROS Report” — Passed→ ERCOT Board Consideration
-
May 17 '11
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NOGRR054 as recommended by TAC in the 4/7/11 TAC Report” — Passed
-
—
Posted since the last meeting