NOGRR #27 · Revision Request

NOGRR027  Revise the Process for Submitting Biennial Unit Reactive Limits (Lead and Lag)

Approved sponsor LCRA posted 2009-07-17 ercot.com
ReasonAttachment E in Section 8 has been superseded by the ERCOT requirement to submit all biennial unit reactive limit tests through the MIS Certified Area. The process for submitting test results through the MIS Certified Area is similar but requires more data than the current form. The circulation of VARs allows the unit to accomplish a lagging reactive test with minimal constraints from the transmission system.
Created2009-08-19
Sections Affected
3.3.2.13.3.2.23.3.2.3Section 8 - Attachment E
Summary
This Nodal Operating Guide Revision Request (NOGRR) deletes Attachment E, Biennial Unit Reactive Limits (Lead and Lag) Verification in Section 8. Attachment E is no longer used as test results are submitted through the Market Information System (MIS) Certified Area. This NOGRR also updates other sections to align with the current process.
Timeline