LPGRR #45 · Revision Request
LPGRR045 Synchronization with NPRR374, Modification of SCR Process and Urgency Requirements
ReasonAlignment with the Nodal Protocols by removing the rapid implementation requirement in the definition of Urgency.
Created2011-10-26
Sections Affected
2.6
Summary
This Load Profiling Guide Revision Request (LPGRR) aligns the Load Profiling Guide with changes proposed by Nodal Protocol Revision Request (NPRR) 374, Modification of SCR Process and Urgency Requirements, which modified the requirements for Urgency.
Timeline
- Oct 10 '11
-
Oct 26 '11
PWG PWG Meeting via WebExPWGRecommended for Approval Recommended for approval“PWG was in consensus to recommend approval of LPGRR045 as submitted.” — Passed→ PWG review the Impact Analysis
-
Nov 9 '11
PWG PWG Meeting via WebExPWGRecommended for Approval Recommended for approval Forwarded → COPS“In consensus to endorse and forward the 10/26/11 PWG Report and the Impact Analysis for LPGRR045 to COPS.” — Passed→ COPS consideration
-
Dec 6 '11
COPS COPS MeetingCOPSRecommended for Approval Recommended for approval“To recommend approval of LPGRR045 as recommended by PWG in the 11/9/11 PWG Report.” — Passed→ TAC consideration
-
Jan 5 '12
TAC Technical Advisory Committee (TAC) MeetingTACApproved Recommended for approval“To approve LPGRR045 as recommended by COPS in the 12/6/11 COPS Report” — Passed
-
—
Posted since the last meeting