LPGRR043  Synchronization with NPRR291, Reduce the Comment Period for NPRRs and SCRs

Approved sponsor ERCOT posted 2011-01-13 ercot.com
ReasonAs a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since LPGRRs have a similar initial comment period, proposed revisions to the LPG revision process are included in this LPGRR to align with the Nodal Protocol revision process.
Created2011-02-23
Sections Affected
2.4.3
Summary
This Load Profiling Guide Revision Request (LPGRR) reduces the comment period for LPGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Profiling Working Group (PWG) meeting.